May in the heart, and on the site as well...
05.05.2023 r.

The end of works at the wastewater treatment plant in Łomża is getting closer and closer.

On a continuous basis, along with the completion of works on individual facilities, start-ups are carried out and installations are put into operation. A new fermentation chamber is already in operation, and the old one is being prepared for renovation. A new biological reactor is put into operation.

A few more months of work and you will be able to enjoy the modernized facility in its full glory.