Within the task: Construction and reconstruction of a sludge and gas line, a sludge dewatering and thickening node and a cogeneration station for the sewage treatment plant in Chrzanów Duży work is carried out on three contractual tasks.
Reinforced concrete works related to the construction of the newly designed facilities have been completed, i.e. pumping stations for thickened and raw sludge, gate valve chambers, and filter chamber. At the Fermentation Chamber, the works are at the stage of dome reinforcement.
Work on inter-facility technological networks is nearing completion, along with the construction of cable lines to power the newly constructed facilities.
Intensive works related to the implementation of protective coatings on the existing and newly designed facilities are underway
In the new building of the cogeneration station, windows and doors were installed and the roof was covered.
The assembly of fittings, devices and technological installations in the newly designed facilities has started.